I've started to build up some Custom Projects an have noted the following bugs:
1. SQX Task Flow commonly gets stuck on a single task and needs to be stopped, then 'Run this task only' in order to progress through that task. To date this has happened with Retest tasks set for: Additional Markets; Higher Precision with real tick data. See attached Config File
2. Retest 'statistic block' in Custom Projects tab is taken from 'Builder' not 'Retest'. Can you modify so that appropriate 'statistic block' is displayed for each type of task within Custom Projects
Thanks
AC1962